Practice Questions for PMP Cert

Next

Q1.Robin, the project manager for CID Corporation is working as a project manager. One of the senior functional managers instructed him to work for the upcoming project. Robin told the manager it is not a project but an operational work because __________.

Ongoing and repetitive

Constrained by limited resources

Planned, executed, and controlled

Creates a unique product or service



Your Answer =


Answer / Explanation:


Cert-Ex™ Exam Simulators, Cert-Ex™ Network Simulator, Cert-Ex™ Cheatsheets are written independently by CertExams.com and not affiliated or authorized by respective certification providers. Cert-Ex™ is a trade mark of CertExams.com or entity representing Certexams.com.PMP™ is a trademark of PMI®.